Crest View Elementary School 
 
Crest View Elementary School
1897 Sumac Ave.
Boulder, Colorado 80304
303-443-6363
http://schools.bvsd.org/crestview
Original construction date: 1958
Report Updated:  8/15/2008 

 News

ATTENTION

Crest View Elementary School will open on time for all grade levels this Tuesday morning, August 19.

Many people have worked very hard to make this happen and their efforts are greatly appreciated.

Crest View will, however, open without a completed cafeteria or hot lunch service until approximately mid-September. We will continue with our plan to provide sack lunches until construction is completed. 

Part of the building will remain a construction zone for the first month of school with restricted access, much like during the spring schedule. Students, staff and parents are asked to respect construction signs and temporary access limits for their safety during this time.

Meet Your Teacher will occur from 2-3 pm on Monday, August 18th. The letter at the following link was mailed to parents August 15th:

Letter to parents

We sincerely appreciate the understanding and patience of the Crest View community as we finalize the construction of what will soon be a beautiful building for our kids for years to come.

 

ATENCION

   La Escuela Primaria Crest View abrirá a tiempo para todos los grados el próximo martes 19 de agosto.

Muchas personas han trabajado muy duro para lograrlo y sus esfuerzos son muy agradecidos.

Sin embargo, Crest View, abrirá sin que se haya completado la remodelación de la cafetería, tampoco habrá comidas calientes hasta mediados de septiembre aproximadamente.  Seguiremos con nuestro plan de proporcionar almuerzos en bolsas hasta que se complete la construcción.

Parte de la escuela seguirá siendo zona de construcción con acceso restringido durante el primer mes de clases, parecido a como estuvimos durante la primavera pasada.  Para su seguridad, les pedimos que respeten las señales de construcción y los límites de acceso temporales durante este tiempo.

El día para Conocer a los Maestros será el lunes 18 de agosto de 2 a 3 p.m.  El enlace de abajo es de la carta que se les envió por correo el 15 de agosto.

Carta a los padres

Sinceramente agradecemos la comprensión y paciencia de la comunidad de Crest View mientras se finalizan las obras de lo que pronto será un bello edificio en el que nuestros niños podrán seguir aprendiendo durante muchos años más.

 

Project Details

Principal: Ned Levine

Architect: Eidos
 
Project Manager: Dave Jorschumb

Contractor: Tower One
 
Project Budget: $5,892,213

View expenditures to date

Design Advisory Team:

Staff
Mark Bauer
Renee Cerny
Lora de la Cruz
Susan Hausle
Ned Levine, principal
Claudia Logerquist
Anne Spalding
Parents
Eric Doub
Mindy Mullen
Charlie Olness
Jim Walker

DAT Meeting Schedule:

2007
May 15, 29
June 12
July 19
October 3
December 5

Contact the DAT: DAT.CrestView@BVSD.org

Project Timeline

Scheduled Milestones
uSD (schematic design) due 07/07; Completed 08/07
uDD (design development) drawings due 09/07; Completed 10/07
uCD (construction documents) due 11/07; adjusted due date 12/07; Completed 01/08
uHard bid
scheduled 12/07; Completed 02/08
uConstruction scheduled 01/08 - 07/09; adjusted to 03/08 - 07/09; Currently under construction

Project Status

Click here for the Construction Update

Novedades del Proyecto de Construcción

Activity that has occurred this period:

Exterior masonry completed. Began work on roofs for additions. Began interior work.

Activity planned for next period:

Classroom and office spaces are scheduled to be completed by August 11th. The stage and cafeteria are scheduled be completed September 19th A letter with more information about what students can expect when they return to school will be mailed home August 9th 

Critical issues:

Please see note above. Office staff will work at Centennial until Aug. 11. Because the cafeteria will not be ready for the start of school, alternate plans for cold breakfast and sack lunch delivery are being made.  Meals will be eaten in classrooms or outside for the first few weeks.

 Budget status:

Within budget.

Schedule status:

Completion of the administrative suite, cafeteria and stage have been delayed. 

 ‭(Hidden)‬ Project Schedule

Chart of progress on Crest View Elementary School project
Scope of Work
Facility Condition Assessment (FCA):  Planned implementation (FCA):
  • HVAC upgrades
  • Replace H&V system in the original 1958 building and the 1970 addition. Replace unit ventilators in rooms 219A, 220, 221, 222 with a roof top unit. Clean and balance system.
  • Electrical service and distribution improvements
  • Upgrade electrical service to meet the needs of the building expansion and currant usage
  • Fire alarm, intercom and clock systems improvements
  • Replace master clock system, upgrade fire alarm to meet code, renovate intercom system
  • Interior finishes upgraded (i.e. ceiling tiles, carpet, wall finishes, etc.)
  • Complete remodel of the administrative area, kindergarten area
  • Roof replacement and repairs
  • Replace failing roof decks
  • Restroom renovations including ADA accessibility where required
  • Upgrade restrooms adjacent to the main entrance
  • Site irrigation system improvements
  • Scope to be defined by Master Plan/Operations
  • Interior signage program
  • Interior ADA approved signage throughout
  • Site paving replacement and repair
  • Repair pavement damaged during construction.
  • Enlarge bike parking area.
  • Site drainage improvements
  • Scope to be defined by Master Plan/Operations 
 
Program Compatibility Assessment (PCA): Planned implementation (PCA):
  • Provide a stage for the gym
  • Add 1100 square foot platform and storage
  • Provide small group instructional spaces
  • Included in the new addition and renovation of the administrative and kindergarten wing.
  • Enlarge the cafeteria and kitchen
  • Add 6500 square foot cafeteria and kitchen
  • Kindergarten addition
  • Demolish portions of the existing cafeteria and kindergarten area and add new 3600 square foot kindergarten space.
  • Enlarge and renovate the administration offices
  • Renovate existing administrative area including new entrance
  • Add additional classrooms for enrollment growth
  • Add 4093 square foot, 4 classroom addition adjacent to new cafeteria
   
Multi-Use Outdoor Facilities (MUOF): Planned implementation (MUOF):
  • Upgrade playground surfacing, equipment, and fencing
  • The scope of all MUOF projects for Crest View will be defined by Master Plan/Operations
  • Provide adequate curbing and drainage
 
  • Replace aged and/or unsafe playground equipment
 
  • Make playgrounds ADA accessible
 
   
Information Technology (IT): Planned implementation (IT):
  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Extend WAN to building, upgrade head end equipment.
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Upgrade existing LAN distribution.
  • Implement VoIP to enhance communications capabilities and reduce cost
  • Install new VoIP telecommunications system.

 

 

 Content Editor Web Part

Groundbreaking March 21, 2008

 

 

 

 

 

 

 Project Illustrations

 
     

Construction photos - June 2008


New classroom and cafeteria addition

 
New classroom and cafeteria addition

 
Kindergarten demolition


Stage craft addition


Cafeteria demolition

 
Cafeteria interior

 
Classroom demolition

 
Office demolition


Breezeway


Outside the front office


Kitchen exterior


Stage addition


Setting steel


Open air Kindergarten


Construction photos - July, 2008